One Health

Website project plan

As of 24 July 2026
Where we stand

Project status

Live statusUpdated 24 July 2026
Status
Awaiting your feedback
Adjusted
14 days
Go live
14 Sep 2026
Build time
9 weeks
Stage 4 of 6 completeDesktop design delivered, awaiting your feedback
Recent activity
  • 16 June Creative concept submitted for approval
  • 24 June Purchase order issued, project confirmed
  • 26 June Security prerequisite completed and returned
  • 29 June Revised landing page concept submitted
  • 30 June Revised concept approved by One Health
  • 1 July Remaining content received, project on track
  • 1 July Copywriting under way, due 4 July
  • 2 July Copywriting submitted for approval, awaiting go ahead to begin design
  • 10 July One Health approved the website copy, design under way
  • 10 July Timeline revised, go live 7 September
  • 16 July Client changed the build from Next.js to PHP on PureCS infrastructure
  • 16 July Development extended to 5 weeks, go live now 14 September
  • 24 July Desktop design delivered for review
  • 24 July Awaiting client feedback to begin development
The plan

Project timeline

Done In progress Upcoming

Sitemap

14 pages

Human Saucer
Done

Creative concept

Revised concept approved 30 June

One Health
Done

Copywriting

All pages, approved 10 July

Human Saucer1 week
Done

UI and UX design

Desktop delivered 24 July. Mobile and animation follow on approval

Human Saucer3 weeks
31 July

Development and QA

14 pages, PHP on PureCS infrastructure, custom CMS

Human Saucer5 weeks
7 September

Go live

Handover to PureCS team on 7 September, then live

One HealthPureCS
14 September
From your side

What we need from you

Approve the web design
The desktop design was delivered on 24 July. Development starts on your approval, and an early sign off pulls the go live date back towards the original.
awaiting
Final copy changes
Any remaining changes to the website copy, so it can be locked before development begins. Changes after that point move the timeline.
before development
Approve the copywriting
Approved on 10 July. The design phase is now under way.
Approved 10 July
CEO quote
A short approved quote for the about page. Photo already received, and it does not hold up the work.
when ready
Revised concept approval
Approved on 30 June, the design phase can begin.
Approved
Supply Chain content
Warehousing, procurement and logistics detail.
Received
Medical projects
Real One Health projects we can feature.
Received
Department emails for routing
The routing inbox for each enquiry type.
Received
Event details for the news stories
Context for the news articles.
Received
Business Development content
Partners and reference projects for the page.
Received
CSSD content
Built from the information available.
In hand
Leadership profiles
The leadership page is paused for now.
Not needed
Channel Management content
No longer needed, the division folds into Business Development.
Not needed
Sign off on the privacy and terms
PureHealth template received, filled and returned.
Received
Each deliverable includes a revision window of three days. Any sign off that runs beyond it carries over to the timeline and moves the go live by the same amount.
Go live
14 September 2026
Prepared by Human Saucer for One Health